| Loup Loup Ski Area Summer Activity
Report for September 18th
As you can see by the accompanying photos, we had a tremendous work
session that focused on 3 fronts this past weekend. The drain fields for
our septic system were worked on by 2 contractors, 3 machines plus
support equipment, and a half dozen additional helpers with the end
result that the drain fields are finished! Hurrah!! The Lodge had its
regular hard core crew prepping and painting with an additional half
dozen weekend warriors coming very close to finishing the first coat of
new paint. Again! Hurrah! Our New Building, not to be out done by the
other two projects, had a steady crew continuing with the roof framing
and getting far enough to cover the upstairs with tarpaper to “weather”
us in! And again! Hurrah!
This coming weekend, September 23rd and 24th, the painting will
continue, and the New Building will be working to extend the roof system
to cover the front deck and ticket service areas, interior framing and
other work to wrap us from the weather, as volunteer help allows.
I have tried in the past to name all the volunteers from each week, but
I’m sorry (& happy!!) to say that I am a bit overwhelmed. Thank you
John, Bill, Jason, Lynn, Barry and... for the roof help, Dave, Aston
(?), Larry, Doug, Jerry, Julie, Billy & others for drain field help, and
Kurt, Sheila, Kurt & crew of others for help on the painting. A Special
thank you to those that helped and whose names I forgot.
For more information, & specifics about the next work session, contact
your local LLSEF Board Member. Or Kurt @ 997-1600. |