| Loup Loup Ski Area Summer Activity
Report for November 6th
Just when it feels as though we have so much to do, we get a great
push towards our Goal. The siding is finished, the deck is getting
close, our plumbing is ready for cover, and the team of Electricians who
worked all Sunday, are closing in fast. Railings and stairs are in the
works.
We always need help, but for the most part, it is more trade specific
from here on out. If you would like to help & are available, please call
ahead so that we can coordinate. We hope to be ready for insulation by
11/13, and drywall within a week following.
Thank you Jeff & Bart for leading teams the weekend of 10/28 & 29. And
thank you Pat for leading the Electricians team, and Wilbur, Leif, John
& son, and the 5 Board members who put time in this past weekend.
For more information, & specifics about the next work session, contact
Chris at 996-2554.
|