Loup Loup Ski Area Summer Activity Report for November 6th

Just when it feels as though we have so much to do, we get a great push towards our Goal. The siding is finished, the deck is getting close, our plumbing is ready for cover, and the team of Electricians who worked all Sunday, are closing in fast. Railings and stairs are in the works.

We always need help, but for the most part, it is more trade specific from here on out. If you would like to help & are available, please call ahead so that we can coordinate. We hope to be ready for insulation by 11/13, and drywall within a week following.

Thank you Jeff & Bart for leading teams the weekend of 10/28 & 29. And thank you Pat for leading the Electricians team, and Wilbur, Leif, John & son, and the 5 Board members who put time in this past weekend.

For more information, & specifics about the next work session, contact Chris at 996-2554.