| Loup Loup Ski Area Summer Activity
Report for November 20th
Apologies to you faithful readers! Although we did make progress
through 11/13, this writer didn’t follow up with that most important
duty to report to you. But here we are a week later & the report is: The
insulation has been installed and inspected & the drywall is stocked in
the building, ready for 2 separate teams to start hanging. The deck is
finished & the wheel chair ramp to the Admin. level is under
construction. The railings on the deck are up and the stairs are due for
installation soon. Now that we have had snow, a major cleanup effort has
been underway.
Between Dan McAuliffe’s Methow Valley Drywall and Gene Bell’s Okanogan
Drywall, both floors will be under the drywaller’s knife, so to speak,
over the next week or so. Painting will follow with interior doors
(ready & waiting), trim, flooring, counters, cabinets etc. just as soon
as it is their turn. Materials and weather permitting, the ramp will be
finished and the stairs, with their own railings, will be installed. We
are hurrying just as fast as we can! If you prey for snow, prey that we
are faster!
Thank you Brad, “the insulator”, Ryan, Luke, Dick, Steve, you faithful
Board Members, North Cascade Builders Supply, and North Valley Lumber.
For more information, & specifics about the next work session, contact
Chris at 996-2554.
|