| Loup Loup Ski Area Summer Activity
Report for November 28th
Over the Thanksgiving break some headway was made working off a bit
of turkey. The wheel chair access ramp to the ticket office level is
finished, but awaits the required hand rails. The central stairway was
also delivered and installed (many a cold finger it took, too!), but
also awaits the required hand railing. The drywall has been hung for
both floors with care (short 2 pieces in the women’s bathroom), in hopes
that the tapers will soon be there.
Last night there was confirmation that the drywallers would start taping
today on both levels. Diebels is building stairs & railings as fast as
they can. Once we finish the drywall, painting will be the last step
before we can install plumbing fixtures etc..
Thank you Roscoe, Tom, Kelly, Dan, Gene & Crew, Dr. Bill, and you ever
faithful Board Members.
For more information, & specifics about the next work session, contact
Chris at 996-2554. |