Report for December 4th
We are coming down the Home Stretch! Our 2 drywall Teams worked hard
& steady last week and finished both levels before the weekend. Our
painter moved in on Sunday and is planning to be finished with the
bathrooms today and the Administrative level tomorrow.
With the painting done, we can move forward with hanging interior doors,
installing plumbing fixtures and cabinets. Our Electrical team is due to
set finish & fixtures this coming weekend. The next 10 days will be
busy, and we will be able to use some help most everyday, but call ahead
before you come up so we can coordinate.
Thank you Gene & Dan and your Crews, Dave of Quality Painter, and the
Board cleaning crew!
For more information, & specifics about the next work session, contact
Chris at 996-2554. |