| Loup Loup Ski Area Summer Activity
Report for December 12th
The New Building took great strides this past week with the help of
many. The painting was finished as predicted last week, the interior
doors were hung, their respective hardware installed, bathroom sink
counters installed, upstairs door and window trim finished, and the
cabinets (custom built off-site) were brought up and installation darn
near done. The Electrical Team swarmed and finished installing all but a
few missing fixtures, a second set of stairs was installed and the
prefabrication of our exterior railings continues off-site.
Our Plumber will start the fixture installation Tuesday afternoon, and a
competing team will try to stay out of his way and begin installing the
stall partitions about the same time. With Opening scheduled for this
Saturday, the pressure is on (not that some of us ever thought it was
“off”!!), but with luck & help, we hope to have the Bathrooms ready for
use, if not the upper level, which should follow within another week.
Thank you Dave of Quality Painter, Peter, Brent, Mike, Pat & your fellow
electricians, and you stalwart Board members!
For more information, & to help with the final push, contact Chris at
996-2554. |